Local 542 Operating Engineer Support
Day Shift – 10
Night Shift – 10
Driver Day – 6
Driver Night – 4
Ridley Yard Day – 3
Road closed 10 pm on 12/20
Road open 6 am on 12/31
Worked round the clock, excluding 12/24 only day shift and no work Christmas Day/Night. Job was completed safely and well ahead of schedule. Would also like to mention Ironworkers Local 401 for their continued assistance throughout this project. It was a tremendous effort by all.
Equipment
260 – 4’ x 20’ x 12” crane mats (used as pad/runway for the 18000)
Manitowoc 18000 w/ 528,000lbs Main weights, 320,000lbs Carbody weights
Totaling - 848,000 lbs
280’ main boom (max), 230’ luffing jib,
Totaling - (about) 520’ tip height
Assist cranes used
550 ton Grove with 264,000lbs Max counterweight (Without MegaWing)
70 ton Tadano
Trucking support
Mats & 18000 – 68 loads
550 ton – 6 loads
Tower removal – 10 loads
Totaling - 84 loads